ProBeya's Estimates page provides a spreadsheet-like batch editor for entering three-point duration estimates (optimistic, most likely, pessimistic) on WBS tasks. These estimates feed directly into Monte Carlo simulations, enabling probabilistic schedule forecasting that accounts for uncertainty rather than relying on single-point guesses.

This feature is designed for project managers and planners who need to capture estimation data efficiently across many tasks and visualize the statistical distribution of each estimate before running simulations.

Overview​

Traditional project scheduling assigns a single duration to each task, creating a false sense of precision. In reality, every task has a range of possible durations: the best case, the expected case, and the worst case. Ignoring this range leads to systematically optimistic schedules.

Three-point estimating solves this by capturing the full uncertainty range for each task:

  • Optimistic (O) -- The best-case duration if everything goes right
  • Most Likely (M) -- The expected duration under normal conditions
  • Pessimistic (P) -- The worst-case duration if significant problems occur

ProBeya's Estimates page makes it efficient to enter these values across all project tasks in a single session, preview the resulting probability distributions, and feed the data into the Monte Carlo simulation engine.

Getting Started​

  1. Navigate to a project and select Estimates from the sidebar.
  2. The page loads all WBS tasks for the project in a batch editor table.
  3. For each task, enter the Optimistic, Most Likely, and Pessimistic duration values.
  4. Select a distribution type for each task (PERT-Beta, Triangular, or Normal).
  5. Review the distribution preview to verify the estimate shape looks reasonable.
  6. Click Save to persist all estimates.
  7. Navigate to the Monte Carlo simulation page to run a simulation using the saved estimates.

Key Concepts​

TermDefinition
Three-Point EstimateA set of three values (Optimistic, Most Likely, Pessimistic) that define the range of possible task durations.
Optimistic (O)The minimum realistic duration. Everything goes according to plan with no issues.
Most Likely (M)The expected duration under typical conditions. The mode of the distribution.
Pessimistic (P)The maximum realistic duration. Significant problems occur but the task is still completable.
Distribution TypeThe statistical model used to generate random samples: PERT-Beta (default), Triangular, or Normal.
PERT-Beta DistributionA weighted distribution where the most likely value carries 4x the weight of the extremes. Mean = (O + 4M + P) / 6. This is the industry standard for schedule risk analysis.
Triangular DistributionA simpler distribution defined by the three points without additional weighting. Mean = (O + M + P) / 3.
Normal DistributionA symmetric bell curve. Requires a standard deviation override since the three-point values define the range, not the shape.
Monte Carlo SimulationA statistical technique that runs thousands of random trials using the estimated distributions to produce a probability distribution of project outcomes.

How It Works​

Batch Estimate Editor​

The BatchEstimateEditor component presents a table-style interface optimized for rapid data entry:

  • Each row represents one WBS task
  • Columns: Task Name, Optimistic, Most Likely, Pessimistic, Distribution Type, Standard Deviation Override (for Normal distribution)
  • Tab/Enter navigation for efficient keyboard-driven entry
  • Inline validation ensures O ≤ M ≤ P (the fundamental three-point constraint)

Distribution Preview​

Each estimate row includes a visual preview of the resulting probability distribution. This small sparkline-style chart helps estimators verify that the distribution shape matches their intuition about the task's uncertainty profile.

For example:

  • A task with O=5, M=7, P=20 produces a right-skewed distribution (long tail of delay risk)
  • A task with O=8, M=10, P=12 produces a nearly symmetric distribution (well-understood task)

Validation Rules​

The editor enforces statistical validity:

RuleDescription
O ≤ M ≤ POptimistic cannot exceed Most Likely; Most Likely cannot exceed Pessimistic.
All values positiveDuration estimates must be greater than zero.
Distribution consistencyNormal distribution requires a standard deviation override if the three-point range is very wide.

Data Flow to Monte Carlo​

Saved estimates are stored as part of the project's Monte Carlo simulation configuration. When a simulation is executed:

  1. The engine reads each task's three-point estimate and distribution type
  2. For each trial (typically 10,000), it generates random duration samples from the specified distributions
  3. Task durations are aggregated through the project's dependency network to compute total project duration
  4. The result is a probability distribution of project completion dates

WBS Integration​

Estimates are linked to WBS (Work Breakdown Structure) elements. The page fetches WBS tasks via the Monte Carlo tRPC routes and presents them in hierarchical order matching the project's work breakdown.

Configuration​

SettingDescription
Default DistributionPERT-Beta is the default distribution type for new estimates. Can be changed per task.
Simulation CountThe number of Monte Carlo trials (configured on the simulation page, not the estimates page).
Standard Deviation OverrideOnly applicable for Normal distribution. Overrides the computed standard deviation with a custom value.

Permissions​

RoleCapabilities
Project ViewerView estimates for project tasks
Project MemberEnter and edit three-point estimates
Project ManagerAll member capabilities plus save batch estimates and configure distribution types
Organization AdminFull access across all projects

The estimates page resolves the project from workspace and project slugs using the server-side tRPC caller, ensuring URL-based access control. If the project does not exist or the user lacks access, a 404 is returned.

Tips & Best Practices​

Estimate as a team

Three-point estimates benefit from diverse perspectives. Have the task owner, a peer, and a technical lead each provide independent estimates, then discuss and converge. This reduces anchoring bias.

Widen the range for unfamiliar tasks

If a task involves new technology, unfamiliar processes, or external dependencies, widen the optimistic-pessimistic range. Narrow ranges on uncertain tasks produce overconfident simulations.

Use PERT-Beta as your default

The PERT-Beta distribution is the industry standard for schedule risk analysis because it weights the most likely value appropriately. Switch to Triangular only if you have a specific reason to give equal weight to all three points.

Revisit estimates as the project progresses

Estimates should be updated as uncertainty resolves. A task estimated at O=5, M=10, P=30 days before design review might become O=8, M=12, P=15 after requirements are finalized.

Check the distribution preview

If the preview shows a shape that does not match your intuition, adjust the values. A nearly flat distribution suggests the team has no idea how long the task will take -- that is a risk signal worth investigating.

Troubleshooting​

IssueResolution
No tasks displayedVerify the project has WBS elements or Monte Carlo simulations configured. The estimates page requires WBS task data to display.
Save button not respondingCheck for validation errors. The batch editor validates all rows before allowing a save. Red-highlighted cells indicate invalid values.
Optimistic exceeds Most LikelyThe three-point constraint requires O ≤ M ≤ P. Adjust the values so the optimistic estimate is less than or equal to the most likely estimate.
Distribution preview not renderingThe preview requires all three estimates (O, M, P) to be valid positive numbers. Empty or zero values suppress the preview.
Estimates not affecting simulationAfter saving estimates, navigate to the Monte Carlo simulation page and run a new simulation. Saved estimates are consumed at simulation time, not in real-time.
  • Monte Carlo Simulation -- The primary consumer of three-point estimates. Runs probabilistic schedule analysis using the saved data.
  • Dependencies -- The dependency graph determines how individual task durations aggregate into project duration. Critical path items have the most impact on simulation results.
  • PPM Projects -- Estimates are project-scoped and linked to the project's WBS structure.
  • Gantt / Timeline -- The timeline view can display estimated duration ranges alongside the baseline schedule.
  • Governance Framework -- Estimation quality metrics can be tracked as governance health indicators.